Posted: Aug 26, 2014

Update - Brid River Bridge Replacement and Main Street Upgrade

The existing bridge has been cut in half in preparation for demolition of the upstream section.

Prior to demolition the piles for the centre pier were to be driven through the existing deck commencing on the 26th of August.  Unfortunately the piling rig has been unavoidably delayed on a project at Cockle Creek.  Another piling rig is being shipped from Victoria and is expected to be on site Monday the 1st of September

For further information contact Dorset Council on (03) 6352 6500.